New build progress May 2016
PROGRAMME AND PROGRESS
COMPREHENSIVE PHASE 1 SCHOOL COMPLETION |
30th March 2017 |
COMPREHENSIVE PHASE 2 SCHOOL COMPLETION (Demolition & External Works) |
19th February 2018
|
CONTRACT DURATION: |
124 weeks |
CONTRACT COMPLETION: |
19th February 2018 |
CURRENT WEEK: |
31 |
CURRENT POSITION: |
On Programme |
PREVIOUS POSITION: |
On Programme |
SECONDARY SCHOOL Envelope Steel Frame is Complete. (revisit for dining hall to allow MEWPS to build above) All concrete upper floors are now complete. Roofing is 80% complete. External Wall SFS and boarding 60% complete. Windows have started. Fire Intumescent Painting is near completion.
Internal works Sole plates for partitions have started this week.
Services and Externals Drainage through the access road to site offices complete.
|